National Steel Bridge Alliance

Estero Parkway

Prize Bridge Information

  • Year Awarded: 2012
  • Year Completed: 2009
  • Location: Estero, FL
  • Award Class: Long Span
  • Designer/EOR: Zep Construction, Inc.
  • Fabricator: FINLEY ENGINEERING GROUP
  • Owner: V & M Erectors, Inc.
  • General Contractor: Tampa Steel Erecting Company
  • Detailer: Lee C ounty D.O.T.

Structure Information

  • Structure Type: Tub Girder
  • Coating System: Paint
  • Span Length (ft): 332/227
  • Structure Length (ft): 559
  • Average Deck Width (ft): 116.6667
  • Steel Weight/Deck Area (lb/ft²): 69.69
  • Amount of Steel (tons): 2278
  • Cost: $35.1 million