How do you shorten a one-year bridge replacement schedule to just four months? Ask the New York State Department of Transportation!

A July flood damaged a 90-year-old bridge that served as a crucial entry to a remote Adirondacks town. Given the need to keep the roadway open plus the rapidly approaching winter season, NYSDOT teamed up with High Steel Structures to expedite the bridge design and replacement.

Visit aisc.org/rapidresponse to find out how the project team used a temporary Acrow bridge and a tightened fabrication and delivery schedule to open the new bridge--just four days before the area’s first snowfall!